- Before
- Issues and clears 15–25 permits a shift across 3 units, desalination and the 33 kV switchroom, with the isolations on separate sheets in another office.
- Now
- Sees every permit, lock and crew on the station drawing, and every request checked before he signs. “I'm the last signature before someone puts their hands in the plant. I need to see every other permit on that equipment.”
One motor test, one crew on the pump, one blocked permit
Kestrel Point Power & Water Station runs three combined-cycle units and four desalination trains for Lumina Utilities. Tuesday 13 October 2026, day shift B, 09:14. Here is what happens next, screen by screen, in the working solution.
- 0109:14
The shift opens on the station drawing, not a list
Callum Reyes · Shift charge engineerCallum issues and clears every permit on day shift B. His board is the station mimic — Unit 1, Unit 2 feedwater, Unit 3, the 6.6 kV board 2BA, the 33 kV switchroom, desalination, cooling-water intake and chlorination — with every isolation point drawn as a lock and every live permit as a pin. The strip above reads 11 live permits, 28 people at work, 27 points locked, 4 requests and 1 held back.
Legend: “Held by a permit · Shared · common certificate · Proposed by a request · Free” · drawing KP-SLD-001 rev K
- 02Since 07:42
Four people inside feed pump BFP-2B
Tomasz Wolak · Performing authority, Voltaro Pump ServicesPTW-26-04817 is the mechanical seal replacement on BFP-2B. Isolation certificate IC-26-1193 holds five points, each proved by Priya Nair before issue — suction, discharge and recirculation valves locked shut, the casing drain locked open, and IP-17, 6.6 kV breaker 2BA-07, racked out, locked and earthed. The job is at step 7 of 9: laser alignment, coupling refitted, hands on the shaft.
Hazards listed: “Stored pressure and hot water · Rotating shaft and coupling · 6.6 kV motor supply · Manual handling of the seal cartridge (38 kg)”
- 0309:15 · Checks run
A test permit asks for IP-17 back — and the board blocks it
Femi Adeyemi · Electrical maintenance leadFemi raises PTW-26-04822, a sanction for test: an insulation-resistance test of the BFP-2B motor, then a 2-minute uncoupled run. Callum runs the checks on the board. The isolation planner builds the test plan from standard plan SFT-6.6-MTR rev C: remove IP-17 so the breaker can be racked to service. The conflict checker finds IP-17 held by 04817, draws the conflict on the diagram and blocks the request.
“A run would turn the shaft they are working on.” · No override on the board
- 04The decision
Two safe routes, and no third
Callum Reyes · Shift charge engineerThe request shows why: the work order assumes the motor is uncoupled, but under 04817 the coupling was refitted at step 6. Callum can re-plan the test after 04817 clears, or ask Femi to change the method — an insulation test only, from the switchboard, with the motor cable disconnected. Override is shown, and not available. Callum re-plans the test for 15:45, linked to 04817, so IP-17 stays in until both are closed, and Femi is told.
“Override · Not available · conflict rule 1, set by the HSE manager”
- 05Sharing a point
One valve, two permits, one common certificate
Conflict checkerSharing is not always a conflict. IP-33, the Train C high-pressure feed valve C-V108, is held by PTW-26-04811 (HPP-C2 bearing change, 3 on) and PTW-26-04812 (CIP tank C internal inspection, 2 on). Both sit under common isolation certificate IC-26-1188, so the board shows the point as shared, and it cannot be removed until both permits are cleared.
“Common isolation certificate IC-26-1188 · cannot be removed until both permits are cleared”
- 0608:44
The drawing changed; the standard plan did not
Isolation plannerPTW-26-04824 is the BCP-3A impeller inspection on Unit 3 after a vibration alarm. The planner compares standard plan BCP-ISO-01 rev C with drawing KP-PID-310 rev F, issued 11 Sep 2026, which added bypass valve 3-V218. The plan lacked it, so the planner adds it as IP-65 and holds the request until an authorised isolator walks it down.
Limit: the isolation planner never marks a point as isolated — only an authorised isolator, in the field, proves it.
- 0708:33
An expired authorisation holds the roof job
Competency checkerPTW-26-04825 is the roof fall-arrest anchor inspection by Brightmast Access. The competency checker checks every named person against the permit type and today's date: Dev Malik's working-at-height authorisation expired on 30 Sep 2026. The request is held until another technician is named or the authorisation is renewed.
“Dev Malik's working-at-height authorisation expired on 30 Sep 2026 · held by the competency checker at 08:33”
- 0809:16 – 09:18
Every lock proved in the field before issue
Ravi Menon · Authorised isolator, desalinationPTW-26-04823, the Strainer D1 basket clean on Train D, passed every check: no live permit holds IP-36 or IP-37, and the crew and isolator are authorised. Ravi locks shut D-V201 and D-V204 and proves each one — lock L-3121, zero pressure at PI-D-201; lock L-3122, zero pressure at PI-D-204. Only then does the decision read “Isolations proved · ready to issue”.
“Both points are locked and tested. Your signature issues the permit; Joel Mensah then accepts it and signs his crew on.”
- 0909:19 · Signed
Callum signs and issues the permit
Callum Reyes · Shift charge engineerThe issue screen shows the work, the area and isolation certificate IC-26-1198 with both points proved by Ravi Menon. The permit is valid to 19:00, then revalidated at handover. Callum signs with his badge and PIN; Joel Mensah accepts on his device and signs his 2 people on, and the permit goes live on the board at Train D.
Agents check and block; only people isolate, issue, accept and clear.
- 1019:00 handover
The night shift acknowledges every permit
Permit chain keeperThe permit chain keeper drafts the handover from day shift B to Aisha Rahman on night shift C: what continues and must be revalidated, what clears before 19:00, the suspended HRSG-1 permit with its isolations in, the two confined spaces that need a gas re-test before re-entry, and the shared point at Train C. Aisha acknowledges each permit, and the acknowledgements are due by 19:15.
“BFP-2B: PTW-26-04817 holds IP-13 to IP-17. The motor test, PTW-26-04822, is blocked on IP-17 until 04817 clears.”