- Before
- Reads 40–60 supplier emails a day and retypes the dates into a tracker. “The supplier told us. It was in an email nobody read for three weeks.”
- Now
- Opens the milestone lines with each supplier email already read and the projects it touches marked; tests recovery options and sends the cited follow-up.
One supplier email, from the winding line to two substations held
Lumina Utilities has 11 long-lead orders open, worth $56.4M, feeding 8 projects. Two 90 MVA 132/33 kV transformers are on the same winding line at Aster Transformer Works: T2 for the new Kestrel Ridge substation and T1 for the Fernhill reinforcement. On Tue 13 Oct 2026 at 07:41, Aster writes. Here is what happens next, screen by screen, in the working solution.
- 0107:41
The day opens on the milestone lines, not an inbox
Rafael Okoye · Senior expediter, grid equipmentEach order is one line of factory milestones — design, core, winding, factory test, ex-works — against the date its project needs it on site. The board reads 11 orders, 7 suppliers, 8 projects fed, 0 late and 5 under 21 days to spare. T2 and T1 each have 7 days to spare. In the right rail, a new email from Ilse Brandt at Aster names both orders.
“…the winding of units 2 and 3 under FC-0219 (your PO 45-118207 and 45-118214) will complete three weeks later than in schedule rev. E: unit 2 on 13 Nov 2026, unit 3 on 11 Dec 2026…”
- 02One click
The email and the revised schedule, read
Supplier mail reader · Milestone trackerRafael clicks Read and apply. The supplier mail reader reads the email and schedule rev. F: two orders, and the cause — conductor late at Aster's sub-supplier. The milestone tracker moves the windings 21 days, T2 from 23 Oct to 13 Nov and T1 from 20 Nov to 11 Dec, and carries the slip down the line using the 49 days from factory to site.
“Carried down the line: T2 on site 4 Jun 2027 · T1 on site 2 Jul 2027 (49 days factory to site)”
- 031 min 50 s later
The winding node slides three weeks, and two substations turn red
Project impact mapper · Contract checkerOn the board the winding milestones jump right with a “W +21 d” marker, and both lines go red at −14 days. The project impact mapper finds both deliveries on the zero-float path to energization: Kestrel Ridge −14 days, Fernhill −14 days. The contract checker finds clause 14.2 of frame contract FC-0219: the delay notice is due by 27 Oct.
“Winding slips 3 weeks on T2 and T1 · Projects late: Kestrel Ridge −14 d · Fernhill −14 d · Delay notice by 27 Oct · 10 working days”
- 04The order
Transformer T2, last promise against today's schedule
Rafael Okoye · Senior expediterThe order page shows T2 — PO 45-118207, $4.82M — needed on site 21 May 2027, now arriving 4 Jun 2027, 14 days late. Rev. E and rev. F sit one above the other, so the moved milestones are plain to see. Every date change carries its source, from the PO acknowledgment of 2 Apr 2025 to today's revised schedule. Delay damages run at $24K a week.
“Schedule rev. F: windings +21 days; on site 4 Jun 2027”
- 05Kestrel Ridge
From the plinth to a customer's connection date
Tom Adeyemi · Project manager, Kestrel RidgeThe project page follows T2 through the site sequence — on the plinth, dress, oil fill and dry-out, site tests, protection and control — to energization, now forecast 14 Oct 2027 instead of 30 Sep. Kestrel Ridge enables the 38 MW Northgate Business Park connection and 4,100 homes at Kestrel Fields.
“Late by 14 days since this morning… The Northgate 38 MW connection date of 1 Oct 2027 would be missed.”
- 06Fernhill
A reinforcement that has to beat the winter peak
Grace Whitfield · Project manager, FernhillT1 drives Fernhill energization, now forecast 12 Nov 2027 against 29 Oct. The second transformer restores N-1 at Fernhill primary, which runs at 104% of its winter rating, and it is needed before the winter peak from 1 Nov 2027.
“N-1 would not be restored before the winter peak.”
- 07Recovery
Four options priced, one ruled out
Rafael Okoye · Senior expediterA second shift on Aster winding line 2 at the contract's acceleration rate ($38K, 9 days on both units). A direct road haul from Ardmouth quay for T2 ($22K, 6 days). Protection works alongside dressing at Kestrel Ridge, from Tom's site sequence rev. 3 ($0, 8 days). Weekend commissioning at Fernhill ($31K, 7 days). The agents' plan takes all four: Kestrel Ridge +9 days, Fernhill +2 days, for $91K against $412K of contractor standby avoided.
Ruled out: “Swap the 90 MVA spare in for T1 — the spare winds from 17 Mar 2027, after T1.”
- 08Approval
Daniel signs the spend and the re-sequencing
Daniel Moreau · Head of capital deliveryRecovery spend over $25K needs the head of capital delivery. Daniel sees the plan — 4 options, $91K, Kestrel Ridge +9 days, Fernhill +2 days — and signs with the meaning of his approval recorded. The plan holds pending Aster's confirmation of the second shift.
Meaning: “I approve the recovery spend and the site re-sequencing”
- 09The reply
A recovery-plan request, cited, for Rafael to send
Expediting action drafter · Rafael OkoyeThe drafter writes to Ilse Brandt: what moved, the need dates it misses, and a request under clause 14.5 for a recovery plan by Tue 20 Oct — the second shift and the days it recovers, conductor from the alternate sub-supplier, and the test-bay slots of 22 Mar and 19 Apr 2027 kept. Rafael edits if he wants and sends it under his own name.
Agents draft; a named person sends. Nothing goes to a supplier on its own.
- 10Day 1 of 10
The delay notice goes on the first day of the window
Sunita Varga · Category manager, power transformers and HV switchgearThe notice under clause 14.2 is drafted in the contract's wording: Lumina became aware of the delay on 13 Oct 2026, and reserves its right to delay damages of 0.5% of the unit price per complete week, up to 10%. Sunita signs and sends it the morning of the slip — day 1 of 10 working days.
“Delay notice sent on day 1 of 10 · delay damages kept claimable”